It has been eight years since the last edition of the JCT contract suite, in which time building safety and sustainability are among the concerns that have come to the fore.
In April, the JCT published the new JCT 2024 Design and Build (DB) contract, the first of its long-awaited suite of 2024 contracts, which addresses these and other issues.
The new suite uses gender-neutral language throughout, with phrases such as 'he shall' being replaced with 'it shall' and 'he may' with 'it may'. This brings it in line with other contracts such as NEC4.
The contract particulars now allow users to enter an email address for the service of notices.
This appears to be an all or nothing approach, though, as there is no option to specify which notices should be issued by email and which by post. Notices are all therefore to be served by the same means.
Practitioners using this contract should thus note the following.
The Building Safety Act 2022 introduced a new role of dutyholder in relation to the Building Regulations.
The JCT 2024 DB contract reflects this new regime with the following provisions.
Amendments to the JCT 2024 DB contract are likely to be required for those working on a project in Wales, though, where the dutyholder role does not currently exist.
The JCT suite has traditionally listed the grounds for the contractor to claim an extension of time under relevant events, with loss and expense to be claimed separately under relevant matters.
However, the 2024 DB contract has been amended as follows.
The suite introduces two obligations regarding the assessment of delay by the employer.
Following the Supreme Court's judgment in Triple Point Technology, Inc v PTT Public Company Ltd [2021] UKSC 29 – covered in a previous Construction Journal article – JCT has amended the liquidated damages clauses.
The new clause 2.29.5 clarifies the position regarding the employer's ability to deduct liquidated damages if the contract is terminated.
Damages will be recoverable until the works are completed or until the contract is terminated. Any losses after termination will need to form part of a general damages claim.
In recent years inflation has had a significant impact on the construction industry in particular.
The JCT 2024 DB contract follows the 2016 edition by allowing the parties to choose which, if any, of the fluctuations options applies.
If none is selected, then option A applies by default.
It should be noted that the full text of the fluctuations options are no longer included in the contract but are to be downloaded from the JCT website.
The JCT 2016 DB schedule 7, fluctuations option A, has also been removed.
The definition of 'fitness for purpose' has been clarified in clause 2.17. This now includes the following.
It should be stressed that this is caveated by reference 'to the extent permitted by the Statutory Requirements'.
The JCT 2016 DB contract includes provisions should the contractor discover fossils, antiquities or other objects of interest or value under clause 3.15.
These set out the requirements for both the contractor and employer if such discoveries are made, and for claiming them as relevant events and relevant matters.
The 2024 contract has expanded on this clause, and now covers asbestos, contaminated material and unexploded ordnance that may be found on the site or during excavations.
This change then flows through to the relevant event, in clause 2.26.4, and relevant matter, clause 4.21.3.
There is a clarification that no relief will be granted where the material was identified in the contract documents or has been brought on to the site by the contractor or any contractor's persons.
What were supplemental provisions under the JCT 2016 DB contract have now been moved into the main contract, reflecting the increased importance of sustainability in business.
Clause 2.1.5 includes a provision entitling the contractor to suggest changes to the works that would benefit the environment.
The wording of the clause has been amended to cover sustainability and environmental impact, as well as environmental performance.
Likewise, clause 2.2.2 now includes the obligation to provide the employer with information regarding the environmental impact of the supply and use of materials and goods that the contractor selects to meet the employer's requirements.
Finally, there are a couple of important changes regarding the settlement of disputes.
While all these changes have been made in the JCT 2024 DB contract, similar amendments are likely in the other contracts in the suite that are due to be issued later this year.
Most notably, JCT has followed NEC and will be providing a new Target Cost Contract. It will be interesting to see how the JCT structures this.
Mark Pountney is a project director at Turner & Townsend contract services
Contact Mark: Email
Related competencies include: Legal/regulatory compliance, Procurement and contracts
10 September | 90 hours CPD | Online
Join our new and improved nine-month course, now including essential project manager soft skills, along with current case studies showcasing industry best practices.
Gain mastery in project management principles and start leading successful projects, people, and teams.
Discover more here