Q: I am a design and build contractor, specialising in high-rise residential developments. Will the new Building Safety Bill cause more disputes over construction projects once it is enacted?
A: The UK government published this long-awaited bill in July. It takes on board the recommendations from the 2019 consultation as well as the Hackitt review, but goes even further by proposing a complete regulatory overhaul. It signals a new era in the way buildings are constructed and which products are used.
To begin with, the new regime will apply to all new multi-occupant residential buildings of more than 18 metres in height, or 6 storeys, in England (see paragraph 22 of the bill). However, existing buildings will also be brought under the system on a phased basis, and in due course the new regime may extend to other types of development.
One of the key changes being introduced is that the Health and Safety Executive must approve a development at three stages, known as gateways: planning permission; pre-construction; and pre-occupation.
The need to accommodate the new regulatory framework, progress through the gateways and achieve the heightened completion sign-off requirements means that the bill, once enacted, is likely to make projects longer and more expensive, at least initially.
The added expense should reduce over time, once the parties to a construction project get used to the new procurement models and collaborative working practices – which seem set to be inevitable and positive by-products of the new regime – and also once quality assurance protocols are established and the necessary training has been completed.
“To begin with, the new regime will apply to all new multi-occupant residential buildings of more than 18 metres in height, or 6 storeys, in England“
The new regime is unlikely to put an end to all disputes, however. Where there are changes or defects are identified, the impacts may be even greater – so unless the contract and records make respective parties’ responsibilities unequivocally clear then it will be tempting for each to fight their corner, and disputes may still arise.
Furthermore, the new regime may cause some additional disputes. The time it is going to take to progress through the gateways and achieve certification is uncertain at this stage. Unless a project programme builds in some extra contingencies for the uncertainty, the cause of the delay to the certification could be contentious and result in disputes.
The hard stop at gateway 3 represents an extra risk as well – in addition to the usual sign-off by the employer or project manager, the parties will also have to convince the regulator that the building is finished and compliant to achieve practical completion. This may cause extra delay, and increases the chance of disputes.
To mitigate this, the parties should allocate risk appropriately in the contract, and keep meticulous records that will deter the party at fault from pursuing a baseless claim. Careful claims management is needed throughout the project, identifying the causes, issuing early warnings, and implementing steps to minimise the impacts. Of course, there is nothing new about these measures.
CONSTRUCTION JOURNAL
Neal Morris and Callum Miller 18 April 2024
BUILT ENVIRONMENT JOURNAL
Neil Hope-Collins 16 April 2024
BUILT ENVIRONMENT JOURNAL
David Browne 09 April 2024