As we shift energy systems away from fossil fuels towards renewable energy, we're changing how we use energy in our homes. But there's a real risk that disabled people and their caregivers will be left behind in this transition.
According to the Joseph Rowntree Foundation's analysis of the Department for Work and Pensions' Households Below Average Income data, disabled working-age adults are almost twice as likely to live in poverty as non-disabled working-age adults (33% versus 17%).
Moreover, their often higher domestic energy needs – spending more time at home, needing additional heating or running assistive-powered technologies like electric wheelchairs – means disabled people are disproportionately affected by fuel poverty.
At the Centre for Sustainable Energy (CSE), we conducted research between April 2024 and June 2025 to understand disabled peoples' experiences across the entire retrofit customer journey, using interviews and workshops with disabled people, caregivers and retrofit professionals.
Our research used mixed methods, which included:
- a household survey with 70 respondents: 94% disabled people and 6% full-time caregivers; a mix of owner-occupiers, private renters and social housing tenants; and representing village, town and inner-city residents and a range of employment statuses
- nine household interviews: seven disabled people and two full-time caregivers; six owner-occupiers, two private rental tenants and one other tenure type; and representing village, town and inner-city residents and a range of employment statuses
- eight retrofit professional interviews and
- three workshops with disabled people, Disabled People's Organisations (DPOs) and retrofit professionals.
While this sample size and nature are not statistically representative of the population as a whole, the findings identify recurring experiences among participants that suggest systemic barriers that prevent disabled households from benefiting from retrofit – and point to practical solutions that would improve the process for everyone.
Communication failures create exclusion
Our survey revealed that poor accessibility of information and advice were major barriers for disabled households, and this view was shared by energy advisers and retrofit professionals.
Inaccessible websites, information not provided in accessible formats, a lack of tailored advice that speaks to specific health needs, the overuse of technical jargon that households didn't understand and information overload were common experiences among those we spoke with.
These challenges can combine to exclude people from even starting the home retrofit process, leaving many unaware of the energy efficiency improvements available to them.
Some considered the grant application process a significant obstacle to the uptake of government-funded retrofit and felt that schemes weren't designed with disabled people in mind. Scheme complexity and the bureaucratic burden of form filling created additional hurdles.
Disabled households described challenges finding trustworthy retrofit installers and, in some cases, feeling pressured to accept an offer.
Stories in local and national media of retrofit-related issues, such as those relating to poor installations of solid wall insulation, meant that overall trust in installers was quite low even before work began.
Disruption and inflexibility remain problematic
The inherent disruption of home retrofit, combined with poor communication from tradespeople, made the retrofit process incredibly stressful for disabled households.
Retrofit planning generally didn't consider a disabled person's needs, which could result in negative financial and health impacts.
Many disabled people have specific needs around energy – for instance, a need for constant access to electricity, being at home throughout the day or needing to avoid particular types of disruption.
Contractors failing to consider these needs can leave people in difficult situations, such as being without electricity or water overnight.
In large-scale delivery schemes, where entire blocks of social housing might undergo retrofit through funded programmes, a lack of flexibility to shape delivery around individual household needs was particularly problematic – heat pumps were repeatedly mentioned in this context.
Installations that might work well for some households proved inappropriate for disabled people with higher warmth needs or different heating patterns.
While heat pumps are not inherently unsuitable for disabled households, the design must be based on the dwelling's heat loss and the resident's comfort, occupancy and hot-water and operational requirements.
A system designed around standardised occupancy assumptions may not provide an acceptable or affordable outcome for a household requiring extended heating periods, higher internal temperatures or additional resilience.
Post-installation handovers were often inadequate and rarely in an accessible format, particularly around use of low carbon technologies and appropriate tariffs.
Participants reported other instances where additional accessibility requirements were also not accommodated.
Possible barriers include restrictions in scheme design, procurement, product availability, funding, programme timescales and the competence or capacity of the delivery team. Further work is needed to establish where responsibility for these decisions sits.
What can retrofit professionals do differently?
The retrofit process needs to be much more customer centred. Having an early conversation with the resident and/or their caregiver to understand their needs – and sharing this information with contractors – could avoid many of the pitfalls described above.
Based on our research, we recommend the following best practice for domestic retrofit professionals.
- Adopt a customer-centred approach: be flexible to meet the needs of the disabled person or caregiver. Remain engaged with the customer consistently from start to finish. Where within their competence and agreed scope, professionals may help residents understand scheme information and identify the evidence required. They should not guarantee funding, eligibility, energy savings or running-cost reductions, and should clearly distinguish technical advice from financial or regulated advice.
- Ensure continuity of coordination and contact: provide the household with a named contact who remains responsible for communication across the whole project. Where several specialist contractors are required, the role of this person is to also coordinate contractor visits, information and handovers to minimise disruption and avoid gaps between work packages.
- Ask about accessibility needs early: early in the retrofit process, ask about the needs of the disabled person and develop an accessibility plan that includes communication preferences and individual circumstances (see CSE's Customer needs checklist). Project teams should establish whether another person has authority to receive information or make relevant decisions. Importantly, involving a caregiver does not remove the need to communicate directly with the resident wherever possible. Capacity should not be inferred from disability or communication difficulty. With the resident's permission, relevant practical requirements should be shared with those who need the information, using appropriate lawful-basis, privacy, retention and security arrangements. Wherever possible, record the adjustment required rather than unnecessary medical details.
- Integrate priority household needs into construction or installation plans: where an accessibility plan outlines a dependence on electricity, water, heating or communications for essential equipment or personal care, the project's delivery plan should define permitted isolation periods, contingency arrangements and an emergency escalation route before work begins. This information should be incorporated into the construction or installation plan, rather than left solely in general resident communications.
- Support residents to ask the right questions: encourage residents to ask installers the right questions (see CSE's Checklist for Disabled households who are making changes to how their home uses energy). Ensure that the resident understands the retrofit process before any work begins and any implications about new technologies – for instance, if using a heat pump will require a change in their heating practices.
- Be transparent about disruption: relevant retrofit professionals should outline and explain the expected disruption that could result from the retrofit process. For example, if electricity or water will be switched off, any expected noise disturbance and how many retrofit professionals will need to enter the home. Provide estimates of the time that could be expected between communications so clients know when to expect future information.
- Provide accessible post-installation support: instructions on how to operate low-carbon technologies should be provided in an accessible format tailored to the need of the household (e.g. Easy Read). Offer appropriate advice on smart tariffs and Smart Export Guarantees. Build trust by emphasising that advice is impartial and you are not trying to sell a tariff.
- Create accessible, jargon-free content: provide information in accessible formats tailored to the household's needs; these needs should be captured through the accessibility plan. This might include Easy Read, sign language and video relay service. Train staff and installers in disabled people's communication and access needs, and signpost staff to disability-specific awareness resources (see Disability Rights UK). Communications and training should ideally be co-designed and/or run by a DPO.
- Organise accessible visits to retrofitted homes: organise visits that are accessible for disabled people and caregivers to local homes or community buildings that have low-carbon technologies installed, so they can learn from neighbours about their retrofit experiences and see technologies in situ.
Critically, accessibility requirements should inform competent technical assessment and design.
Proposed measures should be based on a whole house approach that considers building pathology, ventilation, moisture, overheating, existing services and, critically, the interaction between measures and the occupants' use of the dwelling.
Integrating disability awareness into policy and practice
The Warm Homes Plan is a significant opportunity to address the systemic failings that our research identified, but only if disability is placed at its heart.
Government must ensure disability awareness is fully integrated in to retrofit training programmes and supplemented with disability-specific awareness resources.
Accessibility plans, including details on the communication needs and individual circumstances of the household, should be a standard part of the retrofit process, and developed and adopted from the start of projects.
This should not be solely the responsibility of installers or charitable organisations; stronger regulations and standards would help to ensure consistency across the sector, reducing uncertainty and risk for disabled people and their carers.
Provision of independent energy advice, by advisors who can provide detailed and nuanced advice to disabled households and support them to access grant funding, is also crucial.
This may require support and funding for energy advice organisations to ensure their advisers can access training on disability and retrofit.
For housing providers, it is critical that large-scale schemes consider the needs of disabled households, in terms of what changes are made, the installation process and post-installation support.
When heat pump installations are being planned for social housing, especially through mass retrofit programmes, consideration must be given to the needs of each disabled household and how easy or difficult it will be for them to adapt to new technologies and heating approaches.
Inclusive retrofit isn't just about fairness; it improves quality and trust across the sector. By meeting the needs of disabled households, we create better standards and practices that benefit everyone.
That's how we ensure no one is left behind in the energy transition.
RICS members providing residential retrofit services must follow RICS’ Residential retrofit standard, which has been effective since 31 October 2024. Government-funded projects may also be required to follow PAS 2035:2023 and associated TrustMark requirements.
'By meeting the needs of disabled households, we create better standards and practices that benefit everyone'
Related competencies include: Ethics, Rules of Conduct and professionalism, Housing maintenance, repairs and improvements, Inclusive environments, Retrofit strategy and delivery
Discover the new RICS Member App: CPD on the go
RICS has introduced a refreshed CPD approach that prioritises meaningful, high-quality learning that genuinely benefits your work and is tailored to your specialism, career stage, and the real-world challenges you face.
The new app makes logging CPD simpler and more intuitive, so you can focus on the development that matters to your practice.