For the first five or so years that I spent working in the construction industry, beginning in 1999, I saw an average of two or three claims per project. These claims were most often about disputed additional works, or extensions of time, and occurred for a number of reasons.
While there were exceptions, these claims were usually relatively considered and had some substance, even if the contract entitlement was not always explained correctly. In addition, such claims could usually be managed by the relevant quantity surveyor, or contracts administrator, in conjunction with the project manager, without major incidents occurring.
Over the past 10 years, which I have spent working internationally on major projects in the engineering, procurement and construction field, I have observed that the number of claims per project is increasing. Dedicated claims managers are employed on a long-term basis – at times in excess of a year – both during and after a project has been completed in order to deal with these claims.
With the rise in outsourcing, and the fact that most contractors and subcontractors no longer hold resources in-house to execute works, making them dependent on suppliers, each party has to protect its own commercial interests.
For all involved parties – employers or owners, contractors, and subcontractors – this often means hiring the cheapest bidder following an intense and increasingly lengthy procurement process. Due to this increased competition, and consequent pressure on the price, risk margins are often limited, or even non-existent. This, in turn, prompts greater focus on achieving planned profit from variation orders, or indeed claims.
I have also observed an increase in claims made without a clearly defined premise, where the contract provisions relied on are not set out – or often cannot be found – and where the time and cost effects of this claim have also not been substantiated or are grossly over-inflated.
'Over the past 10 years, I have observed that the number of claims per project is increasing'
There are some companies that are simply greedy, and will exploit any means to increase their profit margin. Unscrupulous parties often rely on the fact that it is usually cheaper for a contractor, or indeed a client, to pay them for extras such as disputed variation orders, or inflated rates to which there is often no entitlement.
In other cases, they may threaten to stop work if they don't get payment and if the alternative is that the contractor or client has to find a replacement subcontractor or contractor – often a lengthy process liable to cost more in the long-term.
This contingency plan can include use of an alternative or second subcontractor, as well as implementing robust project management tools to manage an unscrupulous party – particularly one that is threatening to stop or suspend its works if their claims are not met – including the provision of sufficient staff to handle the extra work this creates.
Clients or contractors often rely on fulfilling conditions precedent when defending a claim, such as compliance with relevant timescales for notification and the submission of substantiation. However, this will often not be enforceable either morally or contractually, especially if this client or contractor has caused events that prevent this timescale from being complied with by the contractor or subcontractor, or where the relevant jurisdiction does not recognise nor enforce the conditions precedent.
Additionally, a claim may trigger more correspondence, which will then cause an even greater burden on the project management staff. Unscrupulous companies will often seek to inundate the other party with documentation to create the impression of a solid case. This documentation will be used later, in more formal dispute resolution hearings, and the company will then exploit the lack of answer or meaningful answers from the other party, irrespective of the strength of the claimant’s case.
This contingency plan can include use of an alternative or second subcontractor, as well as implementing robust project management tools to manage an unscrupulous party – particularly one that is threatening to stop or suspend its works if their claims are not met – including the provision of sufficient staff to handle the extra work this creates.
While there is no clear path when dealing with claims, given the increasing claims culture among companies it is important that robust procedures are implemented in conjunction with clear contract provisions, and that these are properly communicated to all affected. The opportunity for claims should be minimised; but procedures and personnel should be in place to deal with claims when they do arise in order to avoid a costly final account.
'It is important that matters are addressed robustly when they occur and are not allowed to accumulate or remain unresolved'
Merryn Stoyle FRICS is a claims professional and an RICS assessor
Related competencies include: Communication and negotiation, Contract practice
CONSTRUCTION JOURNAL
David Spires 06 December 2023
PROPERTY JOURNAL
Dr Barry McCarron 01 December 2023
LAND JOURNAL
Tim Smith 30 November 2023